Bakker Sliedrecht delivers first two of four fuel efficient module carrier vessels to BigRoll Shipping

29 July 2016

Delivery of fuel efficient 1A Ice Class Module Carrier vessels

Bakker Sliedrecht has delivered the electrical systems of the first two of four Module Carrier (MC-class) vessels, the BigRoll Barentz and BigRoll Bering, which will be operated by heavy marine transportation provider BigRoll Shipping. The 1A Ice Class vessels are specifically designed for the marine transportation of major modules and equipment for large energy projects both on and offshore, to some of the most remote and inaccessible areas on the planet. In the early design phase, Bakker Sliedrecht participated in the design of the innovative propulsion configuration. This configuration ensures safe, reliable and fast transits with particular focus on low fuel consumption, resulting in lower operational costs.

Successful integration of all electrical systems

As an electrical system integrator, Bakker Sliedrecht has been fully responsible for the successful integration of all electrical systems of the MC-class vessels which are DP 2 prepared. Despite the geographical distance between The Netherlands and China, Bakker Sliedrecht enjoyed the good collaboration with COSCO Dalian Shipyard and is looking forward to delivering the final two MC vessels.

Delivered scope of work

For each vessel, Bakker Sliedrecht has been responsible for the engineering, assembly, installation, and commissioning of all electrical systems. A few highlights of the scope per delivered MC vessel are:

  • BIMAC vessel management system
  • 4x alternators 6,6 kV
  • 2 x main switchboards 6,6 kV
  • 2 x HV propulsion systems 5,000 kW
  • 3 x LV thruster drive systems 1,500 kW
  • 2 x LV switchboards 440 V
  • 4 x distribution transformers 1,500 kVA
  • Auxiliary- and emergency generator set

Bakker Sliedrecht participated in the vessels’ sea trials that were conducted successfully in China.

Delivery of remaining MC vessels

Bakker Sliedrecht is still working on the electrical installations and automation of the two remaining MC-class vessels, the BigRoll Baffin and BigRoll Beaufort. Their delivery is scheduled for the second half of 2016 and early 2017.

nieuws afbeelding Bakker Sliedrecht takes care of low voltage switchgear extension IJtunnel
28 June 2016

Creating a Metroform switchboard panel from scratch

Bakker Sliedrecht has received an order from the...

nieuws afbeelding Spare part delivery Seaway Heavy Lifting
08 June 2016

Seaway Heavy Lifting is a leading offshore contractor in the oil & gas and renewables industry that provides...

nieuws afbeelding Bakker Sliedrecht delivers trailing suction hopper dredger Inai Kenanga successfully
28 April 2016

Bakker Sliedrecht engineered, delivered, and commissioned all main electrical installations of the Inai Kenanga....

nieuws afbeelding Bakker Sliedrecht plays a vital role in extending the life time of Heerema’s Balder
26 April 2016

Heerema Marine contractors launched a life time extension program for the Balder, one of their deepwater...