Bakker Sliedrecht successfully replaces 13 kV transformer of Eneco windmill

18 January 2017

Bakker Sliedrecht has successfully replaced the 13 kV transformer of Windmill three of Windmill park II on the isle of Goeree-Overflakkee as additional work to our maintenance contract. 

Because the dimensions of the new transformer were larger than the entrance, Bakker Sliedrecht drew up an ingenious plan to replace the transformer without altering the structure of the windmill.

This challenging project required a transformer measuring van 2x1,5x2,5 meters (length, width, height) to fit through door measuring 0,8 x 2.3 meters (width, height. Widening the door was not an option as altering the structure of the windmill was not allowed. Moreover, the intermediate floor had to be removed without moving the elevator shaft and high voltage installation.

Taking all these conditions into account, Bakker Sliedrecht and her suppliers drew up a tailored plan of approach that ensured a safe working environment and a high quality result. Essential to this plan was the use of a custom designed hoisting beam that was created and certified for this project.

Both the old and the new transformer were disassembled to make them fit through the door. Even the coils of the transformers had to be rotated to reach the desired dimensions.

Because Bakker Sliedrecht had to remove the intermediate floor, scaffolds and fall protection systems were placed to create a safe working environment.

The detailed planning was rewarded when both transformers could be transported without any issues. Eneco: “The project execution really showed the skill and expertise of Bakker Sliedrecht. Because of the careful preparations, this project was executed safely and according to schedule”.

nieuws afbeelding Bakker Sliedrecht extends the lifetime of TESO’s ferry the Dokter Wagemaker
14 November 2016

Bakker Sliedrecht is going to extend the lifetime of the ferry Dokter Wagemaker with 14 years by retrofitting the...

nieuws afbeelding  Learn all about innovations with Bakker Sliedrecht at Offshore Energy 2016
18 October 2016

During the 2016 edition of Offshore Energy, visit the stand of Bakker Sliedrecht to experience our virtual reality...

nieuws afbeelding Bakker Sliedrecht delivers silent electrical propulsion system for state of the art Damen fishery research vessel
14 October 2016

For Damen Shipyards Group, Bakker Sliedrecht is delivering a silent electrical propulsion system for a state of...

nieuws afbeelding Bakker Sliedrecht delivers first two of four fuel efficient module carrier vessels to BigRoll Shipping
29 July 2016

Delivery of fuel efficient 1A Ice Class Module Carrier vessels

Bakker Sliedrecht has delivered the...